BURIING ELECTRIC PIPELINE - PAGLIAN CASALE: INFRASTRUCTURE

INFRASTRUTTURE INTERRAMENTO ELETRODOTTO

The intervention consists in burying the existing power line in the land area of the "Urban Transformation Program - Paglian Casale", through the construction of a double three-phase cable duct approximately 1,500 m long.

The routes have been developed in the area to be urbanized and in the public area.

The new connection is of the mixed overhead / underground type, with a potential of 132 kV.

Client

Sol. Aureum Srl

Sol. Argentum Srl

Sol. Cuprum Srl

Sol. Ferrum Srl

Sol. Ligneum Srl

Taranto 2 Srl Shopping Center

Co.Ge.San. Spa

Urbe 87 Prima Srl

Stahler 2005 Srl

Total value

3,400,000.00

Service

Power line burial project

Level

Preliminary feasibility study completed - Final Project in progress

Year

2012 - ongoing